We are a general contractor and I do estimates following the MasterFormat.
At times we will work on multiples tenders at the same week.
I have setup my layers to follow the divisions 2 to 16 as the MasterFormat ranging from siteworks, metals, wood, mechanical & electrical. My standard traces are setup in layers as well. Every traces were assigned one layer (e.g. if it's carpentry, it's assigned to layer "Div 6 - Wood").
The Standard Traces are set globally across all projects I do. So I want to use Bid Codes to distinguish different projects. I was thinking of having a different set of bid codes per project. One project with "Job 1 - townhouse Plan A, Job 1 - townhouse plan B", another project with "Job 2 - Single family home, Job 2 - Multifamily", etc...
Both projects have common layers (namely carpentry, plumbing, electrical, etc... that was setup in the standard traces). Can I on the fly select which bid code to use when I select the traces I was to takeoff? or do I have to hard code it into the standard traces?